Highway builders have lodged 32 bids for two elevated road corridors along the Ganga and Varuna rivers in Varanasi, worth about ₹25,446 crore together, the National Highways Authority of India (NHAI) said on 27 November.
The two projects, approved by the Cabinet Committee on Economic Affairs in July 2026, run to about 89.2 km and are split into two packages each. The Varuna corridor drew eight and seven bids for its packages; the Ganga corridor drew eight and nine.
Varuna Elevated Corridor
- Length and cost: 43.2 km, ₹10,998.32 crore, under the hybrid annuity model.
- Route: NH-31 to the Varanasi Ring Road along the Varuna, as a mostly elevated six- and four-lane road.
- Time saved: NH-31 to Kashi railway station in about 20 minutes instead of about 40.
It is part of the Varanasi decongestion plan and improves access to the airport, the city's railway stations, Deen Dayal Upadhyaya Junction, Ramnagar Port and the ghats.
Ganga Elevated Corridor
- Length and cost: 46 km of six lanes, ₹14,447.64 crore, also under the hybrid annuity model.
- Route: NH-19 to the Varanasi Ring Road (NH-135B) along the Ganga, with a 910-metre cable-stayed bridge and a 1.32-km extradosed bridge.
- Time saved: average trips cut from about 60 minutes to 20; NH-19 to Kashi station from about 50 to 25 minutes.
Both are designed for speeds of 80–100 km/h and are aligned with the PM Gati Shakti National Master Plan.
What happens next
NHAI will evaluate the bids. The release does not give a date for awarding the contracts or for completion.
Source: official release by the Ministry of Road Transport & Highways, issued through the Press Information Bureau, Government of India (27 NOV 2026 6:02PM by PIB Delhi). Read the full official text: NHAI Receives Overwhelming Response from Bidders for Construction of Ganga and Varuna Elevated Corridor Projects in Varanasi.
How we verified this
VerifiedEvery fact, figure and quotation is taken from the official PIB release (Release ID 2342695) issued by the Ministry of Road Transport & Highways on 27 NOV 2026 6:02PM by PIB Delhi; checked against the source on publication. Story written by BDT from that release; no outside facts added.
Sources
- 1.NHAI Receives Overwhelming Response from Bidders for Construction of Ganga and Varuna Elevated Corridor Projects in Varanasi — Press Information Bureau, Government of India